via email:
The purpose of this project is to provide safe pedestrian access along Crozet Avenue from the Crozet Elementary School to Ballard Drive. Drainage improvements, a sidewalk and a curb-and-gutter will be constructed along the west side including a pedestrian crossing at the school entrance. Plecker Construction Company has been awarded the construction contract and plans to start on March 2, 2015, weather permitting. AMT will assist the County with onsite inspection services and F&R Inc. will perform materials testing on the project. Funding for this project is primarily through a grant from VDOT.
- 03/02/15 – Start of Construction
- 06/30/15 – Substantial Completion
- 07/30/15 – Final Completion
If you would like more information regarding this project, please contact Frank Pohl, Senior Project Manager, by phone (434)-872-4501 x 7914 or by email [email protected].
Â