Streetscape Coming to a Close Soon

Crozet Streetscape - 25 October 2014

Today’s Crozet Streetscape update, via email:

The following progress was made last week:
  • All remaining crosswalks were completed.
  • All remaining mulching was completed.
The following items are scheduled through the end of the project:
  • Final striping and signage installation are scheduled for tomorrow and Wednesday.
  • A Substantial Completion inspection will be held with VDOT the first week of November.
  • Substantial Completion is officially November 18th and Final Completion is December 18th.
For more information on the Crozet Streetscape project, visit www.albemarle.org/crozetstreetscape.

 

I hear they’re going to do a grand opening/ribbon cutting party …

 

2 Replies to “Streetscape Coming to a Close Soon”

  1. Overall, big improvements. However, I have a couple criticisms:
    -natural stone should have been incorporated into the retaining wall and crosswalks,
    -the speed limit on Jarman’s Gap should be raised to 35mph,
    -Oak trees should be planted,
    – the stop light at The Square should be replaced so it matches the new street lamps and so you can see it when you’re actually stopped.

Something to say?