So far, I’d say the traffic disruptions from the Streetscape project have been relatively minimal. Hopefully I didn’t just jinx us all.
via email:
In the next two weeks, improvements between Tabor Street and Library Avenue should be close to 90% complete on the east side of Crozet Avenue. These improvements include curbing, sidewalks, bio-filters, retaining wall, and final grading.
The storm sewer system on the east side of Crozet Avenue has been installed to the Region Ten building. The final section of the storm sewer system, from the Region Ten building to the State Farm building, will be installed after the work in front of the library is complete, which is anticipated in roughly two weeks.
A lane closure on Crozet Avenue is anticipated in approximately two weeks in order to install a new sanitary sewer main.
Tabor Street is complete with final striping to occur within the next week.
For more information on the Crozet Streetscape project, visit www.albemarle.org/crozetstreetscape.