– Crozet Library should be complete in August

– Crozet Streetscape Phase II has all of the rights of way and utility dedications – plan for 14 months construction

– Crozet North Sidewalk – Bid and award in 3rd Quarter 2013 – plan for 3 months construction

– Crozet Parks’ roads will be resurfaced this year